For Immediate Release

West Parking Garage Expansion - Week 36

Notifications:
• Work on the Vertical Expansion and South Expansion continues
o Level 7 – Level 4(West) are barricaded as Construction Zone only.
o Front Street Exit/Entrance Closed
 Owner Work
o Stair 1 & 2 barricaded above Level 4 for Construction
o Stair 3 barricaded above Level 3 for Construction
o Elevator 3 closed during Construction (Front Street Elevator)
o Elevator 1 & 2 closed during Construction (Vine Street Elevators)
• Vine Street Entrance for Battleship Tenants OPENED
o South Side Exit to Convention Center Drive for Battleship Tenants CLOSED throughout September
1. Drive approaches for garage


Here are the scheduled activities for the 36th week of Construction:
1. Install Elevator 1&2
2. Tie-in floor drains on South Expansion
3. Install conduit, pull wire, install lights
4. Elevator work in Tower 3- Final Adjustments
5. CMU installation Elevator #4/5
6. CMU installation South Side/East Side garage
7. Guardrail System Installation
8. Signage to continue
9. EIFS installation Tower #1
10. Roofing Stair #1
11. Window Installation
12. Traffic Coating and Striping
13. Painting
14. Finish Stair #4
15. Installation of mesh panels

Contact:
Jennifer B. Davis
Marketing & Communications Manager
Greater Columbus Convention Center
(614) 827-2538