For Immediate Release

West Garage Expansion Project - Week 34

Notifications:
• Work on the Vertical Expansion and South Expansion continues
o Level 7 – Level 4(West) are barricaded as Construction Zone only.
o Front Street Exit/Entrance Closed
 Owner Work
o Stair 1 & 2 barricaded above Level 4 for Construction
o Stair 3 barricaded above Level 3 for Construction
o Elevator 3 closed during Construction (Front Street Elevator)
o Elevator 1 & 2 closed during Construction (Vine Street Elevators)
• Vine Street Entrance for Battleship Tenants OPENED
o South Side Exit to Convention Center Drive for Battleship Tenants CLOSED throughout September
1. Drive approaches for garage started
• Crane
o Sits on west side of garage near Convention Center Drive


Here are the scheduled activities for the 34th week of Construction:
1. Wreck shoring/reshores from remaining decks
2. Install Elevator 1&2
3. Tie-in floor drains on South Expansion
4. Install conduit, pull wire, install lights
5. Elevator work in Tower 3- Final Adjustments
6. Brick/CMU Installation North Elevation
7. CMU installation Elevator #4/5
8. CMU installation L3 Office
9. Guardrail System Installation
10. Ticket Booth Islands Poured and Ticket Booths to be set
11. Signage to continue
12. High-Bay site work
13. EIFS installation Tower #1
14. Roofing Stair #4 Roof


Contact:
Jennifer B. Davis
Marketing & Communications Manager
Greater Columbus Convention Center
(614) 827-2538