For Immediate Release
West Garage Expansion Project - Week 32 • Work on the Vertical Expansion and South Expansion continues o Level 5 – Level 4(West) are barricaded as Construction Zone only. o Front Street Exit/Entrance Closed Owner Work o Stair 1 & 2 barricaded above Level 4 for Construction o Stair 3 barricaded above Level 3 for Construction o Elevator 3 closed during Construction (Front Street Elevator) o Elevator 1 & 2 closed during Construction (Vine Street Elevators) • Vine Street Entrance for Battleship Tenants OPENED o South Side Exit to Convention Center Drive for Battleship Tenants open on weekends (Fri Night-Mon Morning) • Crane o Sits on west/south side of garage near Convention Center Drive • Brick Installation to begin Thursday 8/16 Stair Tower 1 o Hydro-mobile to be set in Wall St Alley • Hilton Pedestrian Bridge Installation Tomorrow o High St Closed from Vine St to Nationwide Blvd o Only Left turn allowed from Vine St onto High St Here are the scheduled activities for the 32nd week of Construction: 1. Form and pour crashwalls on Level 7 South Expansion 2. Wreck shoring reshores under Level 7 pours 3. Install scaffold and forms for Elevator #4/5 Roof 4. Pour L7 5. Install Elevator 1&2 6. Tie-in floor drains on South Expansion 7. Install conduit, pull wire, install lights 8. Elevator work in Tower 3- Final Adjustments 9. Second Level Reshore Removal (High Bay scaffolding removal) 10. Brick/CMU Installation North Elevation 11. CMU installation Elevator #4/5 12. Guardrail System Installation 13. Ticket Booth Islands Poured and Ticket Booths to be set 14. Signage to start 15. Rest of crashwalls to be poured 16. High-Bay site work to begin 17. Roof installation Tower #2 & #3
Contact:
Jennifer B. Davis Marketing & Communications Manager Greater Columbus Convention Center (614) 827-2538 |