West Garage Expansion Project - Week 31

• Work on the Vertical Expansion and South Expansion continues Monday, July 30th - Friday, August 3rd
o Level 5 – Level 4(West) are barricaded as Construction Zone only.
o Front Street Exit/Entrance Closed
 Owner Work
o Stair 1 & 2 barricaded above Level 4 for Construction
o Stair 3 barricaded above Level 3 for Construction
o Elevator 3 closed during Construction (Front Street Elevator)
o Elevator 1 & 2 closed during Construction (Vine Street Elevators)
• Vine Street Entrance for Battleship Tenants OPENED
o South Side Exit to Convention Center Drive for Battleship Tenants open on weekends (Fri Night-Mon Morning)
o Starting Monday 8/13 Exit to Convention Center Drive will be closed until pedestrian bridge foundation and piers have been completed from the project across the railroad tracks.
• Crane
o Sits on west/south side of garage near Convention Center Drive
• Brick Installation to begin Thursday 8/16 Stair Tower 1
o Hydro-mobile to be set in Wall St Alley


Here are the scheduled activities for the 31th week of Construction:
1. Form and pour crashwalls on Level 6 South Expansion
2. Wreck shoring/install reshores under Level 6 pours
3. Install scaffold and forms for L7 slab pours
4. Pour L7
5. Pour Stairs Tower #3
6. Install Elevator 1&2
7. Tie-in floor drains on South Expansion
8. Install conduit, pull wire, install lights
9. Elevator work in Tower 3- Final Adjustments
10. Second Level Reshore Removal (High Bay scaffolding removal)
11. Ground Level Work to Continue
12. Brick/CMU Installation North Elevation
13. CMU installation Tower #3
14. Guardrail System Installation