West Garage Expansion Project - Week 27

Notifications:
• Work on the Vertical Expansion and South Expansion continues Monday, July 23rd - Friday, July 27th
o Level 5 – Level 4(West) are barricaded as Construction Zone only.
o Front Street Exit is open for Public
 Entrance is closed
o Stair 1 & 2 barricaded above Level 4 for Construction
o Stair 3 barricaded above Level 3 for Construction
o Elevator 3 closed during Construction (Front Street Elevator)
o Elevator 1 & 2 closed during Construction (Vine Street Elevators)
• Vine Street Entrance for Battleship Tenants CLOSED- Monday 7/16- Friday 8/10
o South Side Exit to Convention Center Drive for Battleship Tenants to remain open during time frame
• Crane
o Sits on south side of garage near Convention Center Drive
• Clock Tower Reinstallation
o Saturday 8/4 in the morning
o Vine Street to be closed down during reinstallation

Here are the scheduled activities for the 27th week of Construction:
1. Form and pour columns and crashwalls on Level 4 South Expansion
2. Wreck shoring/install reshores under Level 4 pours
3. Install scaffold and forms for L5 slab pours
4. Install stairs Tower #2/#3
5. Elevator 1&2 to begin
6. Rough-in lighting, power, and communication conduits on Level 7
7. Pull wire for lighting and power on Level 6/7
8. Install Lights Level 7
9. Tie-in floor drains on Levels 5 and 6
10. Elevator work in Tower 3
11. Brick Installation in Battleship Alley (7/16-8/10) (Alley to be closed)

Contact: