For Immediate Release

West Parking Garage Expansion - Week 26

Notifications:
• Work on the Vertical Expansion and South Expansion continues Monday, July 15th- Friday, July 20th
o Level 5 – Level 4(West) are barricaded as Construction Zone only.
o Front Street Exit is open for Public
 Entrance is closed
o Stair 1 & 2 barricaded above Level 4 for Construction
o Stair 3 barricaded above Level 3 for Construction
o Elevator 3 closed during Construction (Front Street Elevator)
o Elevator 1 & 2 closed during Construction (Vine Street Elevators)
• Vine Street Entrance for Battleship Tenants CLOSED- Monday 7/16- Friday 8/10
o South Side Exit to Convention Center Drive for Battleship Tenants to remain open during time frame
• Crane
o Sits on south side of garage near Convention Center Drive
• Ground Floor Garage
o Closed from Monday 7/16- Friday 7/20

Here are the scheduled activities for the 25th week of Construction:
1. Pour S5&S6 (L4 West&East side slab)
2. Form and pour columns and crashwalls on Level 4 South Expansion
3. Wreck shoring under Level 4 pours
4. Install scaffold and forms for L5 slab pours
5. Install stairs Tower #1/#2
6. Elevator Divider Beams Installed (Tower #1)
7. Rough-in lighting, power, and communication conduits on Level 6
8. Pull wire for lighting and power on Level 6
9. Install Lights Level 6
10. Infill colored CMU at Tower #3 West Elevation
11. Tie-in floor drains on Levels 5 and 6
12. Elevator work in Tower 3
13. Brick Installation in Battleship Alley (7/16-8/10) (Alley to be closed)
14. Ground Level Garage DAS construction- Close ground floor



Contact:
Jennifer B. Davis
Marketing & Communications Manager
Greater Columbus Convention Center
(614) 827-2538