For Immediate Release

West Parking Garage Expansion - Weeks 23-24

Notifications:
• Work on the Vertical Expansion and South Expansion continues Monday, June 25th – Fri, July 6th
o Level 5 – Level 4(West) are barricaded as Construction Zone only.
o Front Street Exit is open for Public
 Entrance will be opened on July 5th through July 8th
o Stair 1 & 2 barricaded above Level 4 for Construction
o Stair 3 barricaded above Level 3 for Construction
o Elevator 3 closed during Construction (Front Street Elevator)
o Elevator 1 & 2 closed during Construction (Vine Street Elevators)
• Vine Street Entrance for Battleship Tenants open
• South Side Exit to Convention Center Drive for Battleship Tenants to be open this weekend.
• New Crane
o Sits on west side of garage near Convention Center Drive
o Will be moved on Fridays to accommodate the exit for Battleship Tenants

Here are the scheduled activities for the 23/24th week of Construction:
1. Form and pour columns and crashwalls on Level 2/3 South Expansion
2. Form & tie rebar for Level 8 slab and walls in Tower 1
3. Pour Level 8 slab and walls in Tower 1
4. Install scaffold and formwork for slab in Tower 1
5. Pour Strip poured
6. Wreck scaffold and formwork under pourstrip
7. Rough-in lighting, power, and communication conduits on Level 6
8. Pull wire for lighting and power on Level 5/6
9. Install Lights Level 6
10. Infill CMU at Level 4&5 NW corner
11. CMU to start on Tower #3 west elevation
12. Tie-in floor drains on Levels 4 and 5
13. Elevator work in Tower 3
14. Install scaffold and forms for L3 slab pours
15. Form and tie rebar for L3 slab pours
16. Poured S3 (L3 West side slab) Fri 6/29
17. Pour S4 (L3 East side slab) Fri 7/6

Contact:
Jennifer B. Davis
Marketing & Communications Manager
Greater Columbus Convention Center
(614) 827-2538